Keep target, baseline, forecast, commitment and actual dates distinct

Record a date with its meaning and evidence instead of substituting one date type for another.

Current Revision 2 Reviewed Oct 25, 2026

Applicability

Current Kenta guidance; implementation-source applicability 0.3.0, evaluation scope. Source review does not establish customer production acceptance.

Download PDF (165 KB)Contact support
On this pageInputs and terminologyProcedureVerify the resultWhat happens nextTroubleshooting

Inputs and terminology#

Inputs and terminology
TermMeaning
TargetThe date the project is aiming to achieve; it is not automatically a forecast.
BaselineThe retained reference used to inspect change against the reviewed plan.
ForecastA current prediction with its stated basis; it must not be silently derived from a target or supplier assertion.
Supplier commitmentA versioned supplier date assertion with its own source and meaning.
ActualA source-backed record of an event that occurred. It is distinct from a future promise.

Procedure#

  1. Choose the correct date meaning

    Open the stage date controls or the equipment Delivery section. Identify whether the assertion concerns manufacture, shipping, receipt, installation, testing or handover.

  2. Retain its basis

    Select the appropriate basis, date, owner, linked stage and exact source versions. Leave unknown dates blank and explain the uncertainty.

    Use the controlled change or correction workflow when the record already has a protected date; inspect the current revision before saving.

Verify the result#

The record preserves independently inspectable dates and their meaning, evidence and change history.

What happens next#

A newer assertion flags affected work for review rather than silently replacing a milestone forecast. Recorded actual evidence remains retained.

Troubleshooting#